电器与能效管理技术 ›› 2020, Vol. 586 ›› Issue (1): 94-99.doi: 10.16628/j.cnki.2095-8188.2020.01.016

• 配网自动化 • 上一篇    

计及主动电网结构优化的机组组合*

杜孟珂1, 任燕峰1, 胡永新1, 程浩忠2   

  1. 1.国网北京市电力公司 朝阳供电公司,北京 100124;
    2.电力传输与功率变换控制教育部重点实验室(上海交通大学),上海 200240
  • 收稿日期:2019-08-27 出版日期:2020-01-15 发布日期:2020-03-26
  • 作者简介:杜孟珂(1993—),男,主要从事配网规划、配网自动化等方向研究。任燕峰(1983—),男,工程师,主要从事配网自动化研究。胡永新(1970—),男,工程师,主要从事配网自动化研究。
  • 基金资助:
    * 国家重点研发计划项目(2016YFB0900101); 国家自然科学基金重点项目(513370005)

Unit Commitment Considering Active Optimal Transmission Switching

DU Mengke1, REN Yanfeng1, HU Yongxin1, CHENG Haozhong2   

  1. 1.State Grid Beijing Chaoyang Electric Power Company, Beijing 100124,China;
    2.Key Laboratory of Control of Power Transmission and Conversion (Shanghai Jiao Tong University),Ministry of Education,Shanghai 200240,China
  • Received:2019-08-27 Online:2020-01-15 Published:2020-03-26

摘要: 传统机组组合问题不考虑输电线路的开断问题,忽略了电网拓扑结构改变引起的潮流阻塞。在传统机组组合模型中计及电网拓扑结构的改变,建立了计及主动输电网结构优化的机组组合模型,模型考虑了安全网络约束。通过引入大M法,将主动输电网结构优化模型转化为混合整数规划形式。为了加快模型的求解,采用遗传算法结合混合整数线性规划,研究成果在传统给出各时段机组开停方案的基础上,给出对应时段的最优网络拓扑结构。对修改的IEEE-RTS 24节点的算例表明,计及网络拓扑结构的机组组合能够更有效地降低系统的综合费用。

关键词: 机组组合, 网络拓扑, 安全网络约束, 主动输电网结构优化

Abstract: The grid topology is fixed in the traditional unit commitment,regardless of the transmission line active breaking.In order to solve the problem of transmission line congestion caused by unit commitment,this paper takes into account the change of power grid topology in the traditional unit commitment model,and establishes unit commitment model which takes active optimal transmission switching into consideration.The model includes network security constraint.By introducing Big-M method,the active optimal transmission switching model is transformed into the mixed integer linear programming formulation.In order to speed up the solution of the model,this paper uses genetic algorithm combined with mixed integer linear programming.This paper not only can give the unit commitment schemes at each time,but also get the optimal network topology of each period.An example of a modified IEEE-RTS 24 nodes indicates that the combination of units commitment taking into account active optimal transmission switching can be more effective in reducing the overall cost of the system.

Key words: unit commitment, network topology, network security constraint, active optimal transmission switching

中图分类号: